We have recently bought some land in the South West region of France, we are waiting for planning to be agreed. We have submitted our own plans as under 170m2, but we were wondering if anyone who has been down this road before knows how long the whole process takes before we can start construction.
Any information would be of great help
Many Thanks
Any information would be of great help
Many Thanks
#2
Joined: Mar 2007
Posts: 10,551
Re: self build
We have recently bought some land in the South West region of France, we are waiting for planning to be agreed. We have submitted our own plans as under 170m2, but we were wondering if anyone who has been down this road before knows how long the whole process takes before we can start construction.
Any information would be of great help
Many Thanks
Any information would be of great help
Many Thanks
It depends on the efficiency of the Marie and the DDE in your area I have known it to take two years and as little as 3 months.
#3
BE Forum Addict
Joined: Aug 2008
Location: 32 Gers ; Between Toulouse and Auch
Posts: 1,395
Re: self build
exactly!
we bought land and had a house built 2 years ago; planing took around 6 months, we seems to be the average around here
we bought land and had a house built 2 years ago; planing took around 6 months, we seems to be the average around here
#5
BE Forum Addict
Joined: Aug 2008
Location: 32 Gers ; Between Toulouse and Auch
Posts: 1,395
Re: self build
as my mother used to say
'more haste less speed'
ah well!!
'more haste less speed'
ah well!!
#6
Re: self build
My parent-in-laws had some land near Tours, and I it took them around 6 months for planning permission, and more than a year to construct and finish the place (300m2) - in fact it was closer to two years. Probably didn't help that the father-in-law designed it all himself with no prior knowledge of architecture, though to his credit he was quite thorough and oversaw it all.
#7
Re: self build
Hi,
Our planning permission took three months and that was including a christmas/new year break. We are at Auros, in the Gironde. Our build took about seven months.
Jenny and Charlie.
Our planning permission took three months and that was including a christmas/new year break. We are at Auros, in the Gironde. Our build took about seven months.
Jenny and Charlie.