Burj Dubai facing 9-month delay
#1
Just Joined
Thread Starter
Joined: Apr 2007
Posts: 21
Burj Dubai facing 9-month delay
Burj Dubai facing 9-month delay
by Tamara Walid and Dylan Bowman on Monday, 09 June 2008
The Burj Dubai will now not be finished until August or September 2009, Alabbar has said. The Burj Dubai is facing up to a nine month delay and is unlikely to be finished until August or September next year, Emaar Chairman Mohammed Alabbar revealed on Monday.
Alabbar told reporters in Dubai that the world's tallest building may not be completed until "August or September 2009".
<<snip - got a link?>>
by Tamara Walid and Dylan Bowman on Monday, 09 June 2008
The Burj Dubai will now not be finished until August or September 2009, Alabbar has said. The Burj Dubai is facing up to a nine month delay and is unlikely to be finished until August or September next year, Emaar Chairman Mohammed Alabbar revealed on Monday.
Alabbar told reporters in Dubai that the world's tallest building may not be completed until "August or September 2009".
<<snip - got a link?>>
Last edited by Bob; Jun 10th 2008 at 7:55 pm. Reason: copyright infringement
#2
Account Closed
Joined: Jul 2007
Posts: 7,028
Re: Burj Dubai facing 9-month delay
6.2 acres of parkland and a 30 acre lake my ass! By the time of completion it will be more like 1.2 acres of parkland and an ornamental goldfish pond.
#3
BE Forum Addict
Joined: Aug 2007
Posts: 3,287
Re: Burj Dubai facing 9-month delay
pretty obvious to all that the burj was going to be delayed..
a lot of the outside glass is still only just being put on..
a lot of the outside glass is still only just being put on..
#4
Re: Burj Dubai facing 9-month delay
I like the way they put the blame squarely on the striking labourers.
#6
BE Enthusiast
Joined: Nov 2007
Posts: 385
Re: Burj Dubai facing 9-month delay
I wouldn't be surprised as it isn't even close to being weather-proof so they can presumably only then start the internal work...on 160 floors?!
Oh and opening the Dubai Mall in September is also looking like a struggle seeing as half the roof is missing?
Oh and opening the Dubai Mall in September is also looking like a struggle seeing as half the roof is missing?
#7
BE Forum Addict
Joined: Aug 2007
Posts: 3,287
Re: Burj Dubai facing 9-month delay
a roof? mere trifles...
#8
Soupy twist
Joined: Dec 2004
Posts: 2,271
Re: Burj Dubai facing 9-month delay
Let's be honest here, it's going to end up being a one-year delay. Makes sense really, a completion date of (say) New Year's Eve 2009 allows them to make more of an event of it.
#10
Re: Burj Dubai facing 9-month delay
Burj Dubai will likely only hold the record for 2 or 3 years....
#11
Re: Burj Dubai facing 9-month delay
It's getting silly now. I found a link to some other tower they're thinking about building - The Al Jaber tower, which will be 1800m high.
#12
Re: Burj Dubai facing 9-month delay
Let 'em keep building - keeps our big construction & architecture firms going!! (rapes the planet, but, hey.... whats a bitta scorched earth between friends)